Flood Conditions Impact Pump Station Design
Flood Conditions Impact Pump Station Design
Click Here to Enlarge Picture

Easi-Set Industries, Inc.
5119 Catlett Rd., P.O. Box 300
Midland, VA, 22728
USA



Press release date: February 10, 2014

The Kauffman Ave. Pump Station, in Fairborn, Ohio was two years in the making. What seemed like a straight-forward pump station equipment and generator building became more complex when the City of Fairborn confirmed that, due to its location in a flood-prone area, the building had to be designed to allow only 2 in. of water seepage in any 24-hour period. In addition, they required a 5-year warranty. Norwalk Industries(NCI), an Easi-Set licensed producer, worked with Easi-Set, Concrete Sealants and PS doors to come up with a solution that was within budget yet still met specifications and building code requirements for anchoring the building and for dry, flood-proof design. "The design itself was a challenge because we had never attempted a building with these characteristics," says Robb Smithson, the NCI project manager and engineer. "Some products required long lead times so decisions had to be finalized early in order to meet deadlines."

The 77,300 lbs precast concrete building is 12-ft wide x 20-ft long x 11-ft tall. It is insulated and includes an upgraded electrical package. Not conforming to industry standards, it includes a flood-proof, water-tight door and special anchoring to withstand flood waters. Atop the roof rests a 4,100-lb generator.

"We came up with a detailed plan of action," says Scott Kinnamon, salesman for NCI. "We collected details and ideas and put everything on paper so everyone involved understood what needed to be done and when. "Criteria changed several times throughout the project. Several components, such as the inclusion of the generator on the roof, forced mid-stream design changes. "We had to design a roof that would meet code criteria for slope and weight loads," Smithson says. "After the roof was poured we decided to add another slab for the generator. At times we tested the limits of frustration but in the end came through with a great product for the owner."

For more information about Easi-Set Buildings, go to our website www.easietbuildings.com.

Print | 
Email |  Comment   Share  
Contacts: View detailed contact information.


 

Post a comment about this story

Name:
E-mail:
(your e-mail address will not be posted)
Comment title:
Comment:
To submit comment, enter the security code shown below and press 'Post Comment'.
 



 See related product stories
More .....
 See more product news in:
Fluid and Gas Flow Equipment
 More New Product News from this company:
Custom Buildings are available for various applications.
Restroom Buildings are weather-tight and maintenance-free.
More ....
| Featured Manufacturing Jobs
 Other News from this company:
Water & Waste Facilities Choose the Cost-Effectiveness and Durability of Easi-Set Precast Concrete Buildings
Fast-Track Electric Substation Building Facilitates Immediate Power Needs
Smithsonian's National Zoo Chooses Easi-Set Buildings to House Cheetahs
SoftSound Passes Salt Scaling Test
More ....
 Tools for you
Watch Company 
View Company Profile
Company web site
More news from this company
E-mail this story to a friend
Save Story
Search for suppliers of
Pump or Pumping Stations
Industrial Pump Stations
Water Pumps
Flood Control Pumps
Join the forum discussion at:
The Hardware Bin


Home  |  My ThomasNet News®  |  Industry Market Trends®  |  Submit Release  |  Advertise  |  Contact News  |  About Us
Brought to you by Thomasnet.com        Browse ThomasNet Directory

Copyright © 2014 Thomas Publishing Company. All Rights Reserved.
Terms of Use - Privacy Policy



Error close

Please enter a valid email address