June 29, 2009 (Lithia, Florida) - Central Maintenance and Welding, Inc. (CMW) has completed a major turnaround project for Mosaic Co.'s Riverview (Tampa) Florida sulfuric acid plant.

Specifically, the multi-million dollar project entailed the following key elements for Mosaic's # 8 converter at this facility:

o Demolition of the prior existing converter, ductwork, duct supports, associated structures, and insulation.

o Fabrication and erection of a new converter, ductwork, duct supports, insulation, and foundations as well.

o Demolition of existing super heater, piping, foundations, and insulation.

o Fabrication and installation of new super heater, piping, foundations, insulation, and support structure.

o Removal of existing cold heat exchanger and installation new including insulation, grillage, and new foundation.

As part of this entire project, CMW also performed some other associated plant maintenance including retubing a condenser and economizer.

"Due to our expertise with sulfuric acid plant turnarounds, this project was another success in our commitment to deliver the best total value for our customers," said Steve Bailey, CMW's Project Manager.

For more information, contact Jay Johnson at 1-877-704-7411 or visit www.cmw.cc

Founded in 1966, Central Maintenance and Welding, Inc. provides plant maintenance, plant turnaround, engineering, construction and fabrication services for chemical processing, mining, power generation, and other industrial markets. As an ASME code shop with R, S, and U stamps, CMW's fabrication services include pressure vessels, tanks, heat exchangers, expansion joints, ducts, piping, pipe racks/supports, hoppers, chutes, and more.